Lake City's New Waterfront Park Is Wintering Over. Here's What's Built and What Waits for Spring

November 12, 2026

Behind the storefronts on South Main Street, a worker is putting together the base of a bandshell that has already gone up once. The first set of arches for the Grand Central Park bandshell was taken down after the design changed and the footings had to go deeper. Cadillac News photographed the rebuild in October. Across the site, grass has started along one of the new concrete sidewalks. Most of the remaining landscaping may have to wait until spring because cold weather is closing in.

The park was supposed to be finished by now. It isn't. Two Michigan facts set the delays: Lake Missaukee's waves and the depth of a Michigan frost line. Those same two facts explain why the new finish date lands right at the start of summer.

The lake took the first bite

Lake City broke ground in September 2025 on a $1.87 million park meant to bring more residents and visitors downtown. The site is the old Grand Central Hotel lot, which sat empty along the waterfront for about 20 years after the hotel was demolished. 9&10 News reported that the park's name honors that hotel.

Then came last winter and spring. Planning Commission Chair Craig Ardis told city council that the weather tore up the shoreline where the park was going in. The city's first fix was steel or wood sheet pilings. The Michigan Department of Environment, Great Lakes and Energy didn't approve them. Crews placed cascading boulders instead, set at a slant so wind can help snow and ice slide off.

That boulder line runs from the city dock to the start of the parking lot next to Shoreline Cafe. Cadillac News reported that two Lake City firms, Newell Landscape and Miller Contracting, were doing the work, at an expected cost to the city of $215,000. Ardis put the stakes plainly, as quoted by Cadillac News:

"If this wasn't done, the lake would just keep eating the shoreline away. If you look at the park, we got a promenade sidewalk that goes around toward the edge of the lake, and eventually that could have fallen in the lake."

The shoreline problem spread to other parts of the plan. Beckett and Raeder, the engineering firm on the project, had to review whether the lakeside section of sidewalk needed to move. Moving it could shift other walkways in the park. A new storm drain near the water also needed plans worked out with EGLE. "It's a domino effect," Ardis said.

Then the frost line

The second delay came from below ground. 9&10 News reported on Oct. 28 that the bandshell crew had received plans written for warm climates, with a 24-inch foundation depth. Michigan's frost line requires 42 inches. Crews started building to the shallower plan, then had to tear it out and rebuild to 42 inches.

Even before either of those problems, the site was waiting on wires. Consumers Energy, Brightspeed and Charter began moving overhead utilities underground in September 2025. Conflicts between where the lines were and where they were supposed to go kept that work going until February 2026.

Here is how the schedule has moved:

  1. September 2025: Groundbreaking, and utility relocation begins.
  2. Before July 2026: The original completion target. High water, ice and storm damage pushed it back.
  3. February 2026: Utility work finishes.
  4. August 2026: The city expects completion by the end of September.
  5. October 2026: The bandshell arches come down for deeper footings, and the engineer reports cost overruns to council.
  6. Through December 2026: Construction continues.
  7. Winter: Limited work.
  8. March 2027: Full construction resumes.
  9. June 1, 2027: Target completion.

What the overrun looks like in dollars

At an October council workshop, Beckett and Raeder principal engineer Chris DeGood said the delays and extra work could add $80,000 to $100,000 by the end of the project. As of Oct. 5, the running estimate was about $1.94 million.

Item Figure
Original construction budget $1.87 million
Estimated cost as of Oct. 5, 2026 About $1.94 million
Engineer's projected overage by completion $80,000 to $100,000
MEDC Revitalization and Placemaking grant $935,000
City match, covered by bond $935,000

City leaders told 9&10 News that finishing the park won't take additional taxpayer or city money. The planning commission is applying for more state grants to cover the gap, and it won't reconcile the books until construction is done. "If we reconciled right now, we'd be about $80,000 over," Ardis said. The plan has also been trimmed. The playground will sit on wood chips instead of a rubberized surface estimated at about $50,000.

Ardis told 9&10 News that the same bond paid for replacing lead service lines to about 240 homes all at once. The state's deadline for that work is 2030. That puts part of the park's financing underground, in water lines on residential streets across the city.

The park, section by section

The layout runs south to north along the water, and each section is at a different stage:

  • South end: The bandshell. Its base is being reassembled after the footing correction.
  • Center: The planned community fireplace, behind Hammer's Pub and Grub.
  • North end: The playground. The equipment has been delivered and will be installed once the heavy trucks no longer need that open space to get onto the site.
  • Along the lake: The boulder shoreline and the first sections of promenade sidewalk are in.
  • Edges: North and south parking lots, about 40 spaces combined, were planned as some of the last pieces to build.
  • Throughout: Bushes, trees and grass across the whole park. Cadillac News reported that if crews miss the fall planting window, they'll plant in spring.

Who the bandshell is for

The June 1 target matters because of the bandshell. Ardis told 9&10 News that it will host local gatherings, including car shows and the Fourth of July festivities of the annual Greatest 4th in the North. "You're going to see a lot of activity at the bandshell behind me," he said. He also said the park's purpose ties back to Lake Missaukee itself: "One of the reasons we did a park, because we do have a lot of tourism, because the lake is our biggest draw."

If the schedule holds, the park would be finished about a month before the Fourth. The structure was redesigned around Michigan winters, and the first summer it's built for comes right after its target date.

The block around the fence this winter

Until then, the construction site sits behind a short stretch of downtown restaurants and bars. The City of Lake City's business directory lists these neighbors within a block or two of the site:

  • Bowright Whiskey Company, 103 S. Main St.
  • Pancho Villa Mexican Grill, 106 Main St.
  • The Patio on Main, 113 S. Main St.
  • Town Pump Saloon, 117 S. Main St.
  • Hammer's Pub and Grub, 118 S. Main St., whose menu covers burgers, sandwiches, pulled pork, wings, salads and kids' meals.

The park is only one piece of the downtown work. Ardis told 9&10 News that it's part of about $6 million in city infrastructure spending across three projects. Next up is the street in front of these storefronts. On March 16, 2026, the Michigan Department of Transportation announced a conditional $1,944,805 Transportation Alternatives Program commitment for "M-66 Lake City Pedestrian Safety Improvements." The project covers refuge islands, bump-outs, sidewalk, crosswalks and safety lighting. In the city's 2025 project description, possible crossing locations included spots near Mitchell and John streets, by the city park and the businesses next to it, and at Union Street. The city also discussed refuge islands near Hill and Henry streets. If those plans go ahead, the finished park would connect to Main Street by new crossings.

Heading into its second winter, the park has a boulder shoreline, some sidewalk, a new stretch of grass and a bandshell base sitting on 42-inch footings. Full crews are scheduled to return in March.

We'll keep following Grand Central Park through the winter and into that June 1 target. If a home within walking distance of Lake City's waterfront is part of your own plans, Daniella Bell Group would be glad to talk through what the new park and the M-66 work could mean for those few blocks. Find Your Beautiful Life.